27 of 80 turbines installed
End-2022 completion foreseen
Strike price of Eur143.6/MWh
The 480 MW Saint-Nazaire wind farm off the Guerande Peninsula in northwest France has produced the country’s first offshore wind power, EDF Renouvelables said June 10.
Not registered?
Receive daily email alerts, subscriber notes & personalize your experience.
Saint-Nazaire was one of six French offshore wind projects awarded concessions back in 2012 and 2014. The Eur2 billion EDF/Enbridge-owned project has a strike price of Eur143.6/MWh ($152/MWh) under a state-negotiated contract.
“By the end of 2022, 80 wind turbines in the park…should be installed at sea and produce a total of 480 MW, equivalent to the annual domestic consumption of 700,000 people,” EDF Renouvelables said.
Some 27 GE Haliade 6 MW turbines have been installed to date following completion of a first unit in mid-April, while state network operator RTE has completed connection.
EDF Renewables is involved in three other offshore wind projects under construction at Fécamp (498 MW), Courseulles-sur-Mer (450 MW) and Port-Saint-Louis-du-Rhone (the 24 MW Provence Grand large floating wind project), plus one under development off Dunkirk (600 MW).
Year-ahead French baseload power has settled above Eur300/MWh on the EEX exchange since May 11, averaging Eur310.82/MWh June to date versus Eur243.15/MWh for the corresponding German contract, regarded as a benchmark in European power.